With every month that passes, we get busier and busier. May has seen so many different developments, let’s recap a few! Every aspect of the Chapel build gets our full attention, from the garage doors to the colour of the guttering. Water holes were emptied and filled with concrete before the beams and concrete blocks…
Tag: scaffolding
A Team Visit
The ground floor is finally in and the 3fD team wanted to test the waters and have a look around at all the exciting developments that have been happening in the Chapel as of late. Don’t step back – that’s wet concrete floor in the entrance. It is changing so much! We can really see ourselves…
Fancy a tour?
You’ve seen the pictures, you’ve watched the videos, now take your own personalised tour of the 3fD Chapel Gym! Stretch & click below… Gym Showroom
Clip of the day
A picture tells a 1000 words, a video says it all. Click play…
April Showers
April had many hurdles to overcome, mainly with the floor. With the increased amount of water seeping in from the River Test, filling the holes in the Chapel, even the digger struggled not to sink through the floor. All that soil has to go somewhere.. We are thankful April came with a new roof !…
Flooding of Whitchurch
‘Evil Atlantic depression’ is what the random heavy downfall of rain is being blamed on, and with rain comes floods, and it didn’t take long for the water to rise through the entire Chapel. We weren’t the only ones effected in Whitchurch though, with local shops and pubs feeling the stain from the rain and…
Ground Designs
You’ve seen the first floor, now it’s time to have a look at our plans for the ground floor. Here is a more detailed look at the floor plan ↓ Make sure you visit our blog regularly so you can be kept up to date on all things Chapel!
Roof Roof
The main Chapel roof is on, and in only one day! How you ask? By using Nulok roofing system! Firstly Nulok battens are fixed to the rafters in the conventional way, replacing traditional timber battens. Then specially designed Link Channels are snap fitted to the battens to form an interlocking grid system. And finally our slates are slotted…
February
The back wall was taken down in January – before it fell down and we are now ready to rebuild. For the first time we have building materials on site, rather than the constant removal of rubbish to date. With scaffolding up for the roofers, this is the first time that the team has seen the Chapel…
The Team
Our team is growing as are the developments with the Chapel! Even with the English weather, we are pushing on to hopefully move in before Christmas and once again have our tree lit up outside as is tradition in Whitchurch. Keep an eye out for more updates..
Early January
Early January brought a welcome relief from the rain, but it was bitterly cold. Phil constructed a ‘home inside the Chapel’ so he and the team could keep warm when they were having a cup of tea. Essential. Removing the render has made a huge impression on the building. Painstaking work, but really worthwhile. Work is continuing on…
December progress
Clearing the site has revealed the Chapel for the first time. The front roof slates have been removed an a tarpaulin is now keeping the front section relatively water tight. Turning our attention to the rear workshop, we notice with horror that the rear wall is badly compromised. It has been pushed over centre by…