Building Desks and Moving to the Main Studio

It has been a while since anything was posted on here but in case you haven’t heard 3form Design has officially moved into the chapel! Ian and George are still here carrying out work on the building. Outside things are looking much the same as they have the past few weeks but inside everything is…

The Clock Will Soon Be Ticking

It is hard to keep up with the progress at the chapel right now. Things are moving along so fast that, even as this article is written, big decisions are being made rapidly here in the office. It certainly is an exciting time as we push on through the final couple of months of this…

One Step at a Time

Last week one of the major features, that we have been extremely excited about, finally arrived – the stairs! As with most of the other aspects of the building, these stairs were custom built to Austen’s design. You can check out the video of the installation below. 3fD Chapel – Installing the Front Staircase from…

Another Brick in the Wall

There is a lot of work happening inside the chapel but, as you may have noticed, the exterior is also getting a lot of attention now. More of the aluminium cladding has been fitted, the ground works are underway and the brick enclosure at the front of the building is well on its way to…

What is happening with the stained glass window?

Almost everyone who has taken interest in the build has asked the same question: What are you doing about the stained glass window? Until now we have been unable to fully answer that question but after much debate and head scratching we can.   The old stained glass window is in very poor condition and…

Super-club circuits, plumber punch-ups and a bit of desk sizing…

Last week saw the stud work being built, the first of the plumbing and a lot of planning being done for the electrics. Visually things are changing every day, now that we are this far into the build. We even have some temporary stairs! The stud walls have been put up in the upper-floor rear section…

A level playing field

It has been a very busy month at the chapel and the pace is continuing to quicken as we approach the end of the year. Last week saw the screed go down on the upper and lower floors which was an unusually rapid process. The screed mix that we opted for was MPA Liquid Screed…

Another Refurbishment..

The Chapel build isn’t the only thing getting a new look.. As a Product Design Consultancy, design is everything. From the way we want you to feel when you step into our office, to the motivation and inspiration our website should fill you with when you click on our logo. Which is why we have launched a BRAND NEW…

Cobwebbed Chapel

One of the local residences of Whitchurch, Noel Privett, sent in this absolutely beautiful picture he captured one dewy morning. We absolutely love it! In fact we aren’t the only ones as it was featured in the Silk Mill Calendar for the month of July!   Isn’t it wonderful! If you have captured any pictures of the…

It’s Here!

  The chapel sign has finally arrived! So if you couldn’t find us in Whitchurch before you shouldn’t have any problems now! A rather sizeable 8.5ft tall! Make sure you keep an eye out for us!  

MAYbe the busiest month so far

  With every month that passes, we get busier and busier. May has seen so many different developments, let’s recap a few! Every aspect of the Chapel build gets our full attention, from the garage doors to the colour of the guttering. Water holes were emptied and filled with concrete before the beams and concrete blocks…

The Team

Our team is growing as are the developments with the Chapel! Even with the English weather, we are pushing on to hopefully move in before Christmas and once again have our tree lit up outside as is tradition in Whitchurch.     Keep an eye out for more updates..