Building Desks and Moving to the Main Studio

It has been a while since anything was posted on here but in case you haven’t heard 3form Design has officially moved into the chapel! Ian and George are still here carrying out work on the building. Outside things are looking much the same as they have the past few weeks but inside everything is…

Have You Seen the New Window?

Unfortunately it has again been a while since we last managed to write a blog post, but here we are at last with an update on the progress. Lots has happened, as you can probably guess, and we are all here waiting eagerly for the move in date to be officially decided. One thing that…

The Clock Will Soon Be Ticking

It is hard to keep up with the progress at the chapel right now. Things are moving along so fast that, even as this article is written, big decisions are being made rapidly here in the office. It certainly is an exciting time as we push on through the final couple of months of this…

One Step at a Time

Last week one of the major features, that we have been extremely excited about, finally arrived – the stairs! As with most of the other aspects of the building, these stairs were custom built to Austen’s design. You can check out the video of the installation below. 3fD Chapel – Installing the Front Staircase from…

Choosing the Stained Glass and Making an Entrance

The past few weeks at the chapel have seen many changes take place. The plastering is almost complete and as a result the interior is now looking amazing. Outside the ground work is underway and the brick walls making up bin enclosure has been finished. Today, Shelagh Davies came with her assistant, Barrie, to measure…

Another Brick in the Wall

There is a lot of work happening inside the chapel but, as you may have noticed, the exterior is also getting a lot of attention now. More of the aluminium cladding has been fitted, the ground works are underway and the brick enclosure at the front of the building is well on its way to…

A busy place to be

The chapel is a very busy place to be right now with a lot of different jobs happening simultaneously. Plastering has begun, electrics continue to be fitted, fire systems are being installed and lots of work is being done in preparation for the staircase installation, lighting and flooring. One of the most exciting moments recently…

Did you notice?

Happy new year everyone! We hope you all had a fantastic Christmas break, we know we certainly did. Have you noticed the new windows? In the last few days prior to the Christmas break the guys worked tirelessly to lift these massive windows into place. The side windows went in first as these were lighter…

A guided tour

From outside the chapel there have been many visible changes. If you have passed by the building regularly over the last year you will have seen it evolving and may have wondered what was actually going on – so we thought we would take you on a tour allowing you to step inside the front…

Super-club circuits, plumber punch-ups and a bit of desk sizing…

Last week saw the stud work being built, the first of the plumbing and a lot of planning being done for the electrics. Visually things are changing every day, now that we are this far into the build. We even have some temporary stairs! The stud walls have been put up in the upper-floor rear section…

A level playing field

It has been a very busy month at the chapel and the pace is continuing to quicken as we approach the end of the year. Last week saw the screed go down on the upper and lower floors which was an unusually rapid process. The screed mix that we opted for was MPA Liquid Screed…

Another Refurbishment..

The Chapel build isn’t the only thing getting a new look.. As a Product Design Consultancy, design is everything. From the way we want you to feel when you step into our office, to the motivation and inspiration our website should fill you with when you click on our logo. Which is why we have launched a BRAND NEW…